Brook House Primary School

The Lion Academy Trust

This project comprised the fit out of a new shell and core building over two levels for the purpose of creating a new 420 place two form entry primary school.

The works comprise the internal fit out including internal walls and linings, building services and fixtures, fittings and equipment of the ground and first floors, the external amenity and play space to the east of the building, and adjustments to the perimeter fencing.

  • Ground Floor – classrooms, group rooms, toilets, shower, ICT strong room, meeting rooms, offices, kitchen, storage, bin stores, large hall, reception/admin area, entrance/waiting area, DDA lift, plant room, two stairs
  • First Floor – classrooms, group rooms, toilets, hygiene room, community room, resource room, training room, staff room, offices, storage
  • External Works – aluminium frame canopy, tarmac area, timber picket fence and gate, rendered wall finish for proposed artwork, external signage, four new gates and associated fencing, replacement and modification of fencing around the western playground to incorporate the playground into the school perimeter.
Share...Share on FacebookShare on Google+Tweet about this on TwitterShare on LinkedInEmail this to someone
Download PDF

Project Name: Brook House School

Location: Sydney Street, London, SW3 6NP

Value: £2,850,000

Principal Consultants: Mace

Project Duration: 34 weeks

From the outset we have been very pleased with how Logan Construction have approached this project and how diligent and thoughtful they have been throughout. The success of this project is down to a combination of our design and school operating experience matched by Logan and our technical advisors’ appetite to work collaboratively with Newlon and the Department of Education to keep things on the productive track we see before us.